How long does it take to connect a meter to our building site?

It depends on how many steps below you need completed to connect your site:

  1. First, check for underground power installed on your block. Look for a shiny green dome or call Western Power on 13 10 87 to confirm or to install your dome.
  2. Apply for a new connection with us - we'll process your request within 3-5 days and issue you with a reference number:
  3. Pass on the reference number/s on to your builder or electrician.
  4. Your builder/ electrician will liaise with Western Power to get your meter installed and connected to the grid. Allow 5 working days in a metropolitan area, and up to 10 working days in rural areas.